KTX Songdo Station Integrated Transfer Center
The KTX Songdo Station Integrated Transfer Center is expected to serve more than 20,000 passengers per day when construction works to connect the Suin Line, KTX Line, and the East-West Line are complete

More specifically, the KTX Songdo Station Integrated Transfer Center will feature
shops, stores, offices, and accommodation facilities targeting transferring passengers, as well
as public transport platforms and parking lots (total area: 28,248㎡).
The entire site will be designated as a Special Planning Zone, and private developers will be
selected through an open bidding process during the second half of 2019. Once the developer is
selected, the Korea Rail Network Authority will work with a Special Purpose Company (SPC)
created for the project, and finish all construction works by 2023 when the KTX will be ready
for service. When complete, the KTX Songdo Station Integrated Transfer Center will process
roughly 20,000 passengers on a daily basis from three different railways - Suin Line (open in
2016), KTX Line (open in 2023), East-West Line (open in 2024) - making it a major public
transport hub in Incheon.
Summary of the Project
- Location: Songdo Station, Ongnyeon-dong, Yeonsu-gu, Incheon
- Site: 28,248㎡ (8,595 pyeong)
- Project Duration: 2018 ~ 2023
- Developers: SPC (pending)
Total Area (㎡) | Land Price | Building Coverage Ratio | Floor Area Ratio |
---|---|---|---|
28,248 | Post-development Appraised Value | 70% | 1000% |
Business Type | Plan Details |
---|---|
Transfer Facilities | Transfer stations, parking lots |
Transfer Support Facilities | Shops, stores, culture and meeting facilities, offices, accommodation facilities, recreation/entertainment facilities, etc. |

Inquiries
- Investment Promotion Division (032-440-3286~8), Incheon Metropolitan City Government
- Affiliated Organizations: Urban Development Planning Division (032-440-4534), Incheon Metropolitan City Government